The Project
To support the increased production requirements of the General Mills factory in Oinofyta, there was a need for an upgrade, initially of the existing substation, for the new 2,000 square meter building developed adjacent to the existing facilities.
KAFKAS Contribution
In collaboration with the technical company of Mr. Emm. Kourakis and his external partners Kartala-Mittaki, KAFKAS designed and supported a complete solution for the upgrade of MV panels, as well as two new LV panels of 3,200A. Additionally, for the needs of the project, KAFKAS began the collaboration by supplying a grounding system and subsequently MV and LV cables, along with supporting materials for connection, routing, and protection. To complete the collaboration for the main project, KAFKAS supplied LED lighting fixtures for the main production area.